PHOTO GALLERY

In May, in the Cosmopolitan Mihai Viteazul 1 construction site, the process of formwork, reinforcement and casting of diaphragms and pillars for Basement 1 took place.

In Cosmopolit Mihai Viteazul 1 construction site, the 3rd, 4th and 5th casting phases for Basement 2 – diaphragms and columns took place in April. At the moment work is underway to extend the scaffolding for Body B, Basement 1.

At building site Mihai Viteazul 1, the third casting stage for basement 2 was completed for partition walls and pillars.

Reinforcement of load bearing walls and of the independent pillars for basement 2 started in February on the building site Cosmopolit Mihai Viteazul 1.

In January, slab foundation pouring and trowelling were achieved for Cosmopolit Mihai Viteazul 1. Further on, actions for supporting pillars and perimetral walls were marked with the assistance of the topometrist specialist.

At building site Mihai Viteazul 1, digs for the foundation layer ended and the work on the baluster layer for the foundation plate continue throughout December.

At building site Mihai Viteazul 1, digs for the foundation layer continued and work on the baluster layer for the foundation plate started in November.

In Cosmopolit Mihai Viteazul 1 site, we completed the process of drilling, reinforcement, casting piles and crown beam. We continue the excavation for the foundation of the block and the installation of the supports. Also last week, reinforcement, formwork and foundation casting activities for the crane location were carried out.

In Cosmopolit Mihai Viteazul 1 we started the excavation work for the foundation of the mansion, and in parallel the pouring of the crown beam continues.

Foundation digs for the building Cosmopolit Mihai Viteazul 1 starts, while, simultaneously, top beam casting works continue.

Post construction works end and work on the top beam casting for the building starts.

Post boring, reinforcement and casting work ended and top beam works have started at the building site Cosmopolit Mihai Viteazul 1.

All works related to post construction stages continue at the building site Cosmopolit Mihai Viteazul 1.

Post boring, reinforcement and casting works within building site Cosmpolit Mihai Viteazul 1 have started.

Work on the new residential project Mihai Viteazul 1 has commenced. Currently, the old buildings here are being
demolished and the construction land is being cleared.

Back to Projects Progress

FIND OUT THE LATEST NEWS

Subscribe and stay in touch with the latest offers